You don't have javascript enabled. Good luck with that.
Pencarian
Pelebaran Jembatan Kali Cagklak Cibubur Capai 20 Persen
.
photo Nurito - Beritajakarta.id

Caglak River Bridge Widening Project Targeted to Finish in December

Caglak River bridge widening project on Jalan Lapangan Tembak, Cibubur, Ciracas, East Jakarta with total budget of Rp 1 billion now has reached 20 percent.

Its process has reached 20 percent

East Jakarta Bina Marga Sub-department Head, Muhammad Soleh explained, Caglak River bridge widening project has been started from one month ago. It is done to follow up resident's request through Musrenbang.

"Its process has reached 20 percent," he added, Thursday (11/7).

Caglak River Bridge Proposed For Widening

In this stage, his side has removed the utility network, put a few of hollow blocks into fabrication process, and prepared to install the piles on Friday (11/8)

"This project is targeted to complete in mid of December," he stated.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1039 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye904 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye546 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye447 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye380 personAldi Geri Lumban Tobing